Add approx start dates / month to milestone timelines
Browse files Browse the repository at this point in the history
  • Loading branch information
liangjh authored Jan 17, 2024
1 parent 08f2c17 commit ff9e09b
Showing 1 changed file with 3 additions and 3 deletions.
6 changes: 3 additions & 3 deletions applications/dot_etl.md
Original file line number Diff line number Diff line change
Expand Up @@ -105,13 +105,13 @@ We are currently in research phase; Development / coding has not started on thi

### Overview

- **Total Estimated Duration:** 8 months (from start of implementation)
- **Total Estimated Duration:** 8 months (start: June 2024)
- **Full-Time Equivalent (FTE):** 0.25
- **Total Costs:** 26,000 USD

### Milestone 1 — ETL of Relay Chain + Google BigQuery Integration

- **Estimated duration:** 3-4 months (from start of implementation)
- **Estimated duration:** 3-4 months (start: June 2024)
- **FTE:** 1
- **Costs:** 8,000 USD

Expand All @@ -132,7 +132,7 @@ We are currently in research phase; Development / coding has not started on thi

### Milestone 2 — ETLs for Selected Parachains, Extensions

- **Estimated Duration:** 3-4 months
- **Estimated Duration:** 3-4 months (start: Oct 2024)
- **FTE:** 1
- **Costs:** 18,000 USD