Project Schedule

Timeline estimate

Component Aspects Time Estimate
Project Infrastructure
  • Directory structure
  • Build process
  • Server
1 week
Site Infrastructure
  • Room management
  • Activity listing
  • Authentication
  • Groups (joining/rejecting/redirecting)
2 weeks
4 client-side activities
  • PPF
  • Money Creation
  • When Graphs Mislead Us
  • Income and taxes
2 weeks
Room lifecycle
  • Data collection
  • Report generation
  • Activity controls
  • Group creation and destruction
2 weeks
Pizza
  • Drag and Drop toppings
  • Dough stretching
  • Station navigation
  • Pizza heap
  • Layout
  • Player allocation / rounds
  • Report graph definition
4 weeks
Cacao
  • Layout
  • Report graph
  • Transaction verification
  • Teacher controls
2 weeks
Gas Station
  • Layout
  • Player allocation / rounds
  • Non responsive player detection / recovery
  • Teacher controls
4 weeks
Income Distribution
  • Layout
  • Teacher controls
1 week
Earning Credit
  • Layout
  • Survey
1 week