Project Estimation - FUTURE

Date: 28/04/2023

Version: V2

Estimation approach

Consider the EZWallet project in FUTURE version (as proposed by the team), assume that you are going to develop the project INDEPENDENT of the deadlines of the course

Estimate by size

Estimate
NC = Estimated number of classes to be developed 7
A = Estimated average size per class, in LOC 300
S = Estimated size of project, in LOC (= NC * A) 2100
E = Estimated effort, in person hours (here use productivity 10 LOC per person hour) 210
C = Estimated cost, in euro (here use 1 person hour cost = 30 euro) 6300
Estimated calendar time, in calendar weeks (Assume team of 4 people, 8 hours per day, 5 days per week ) 1.2

Estimate by product decomposition

component name Estimated effort (person hours)
requirement document 30
GUI prototype 20
design document 25
code 90
unit tests 90
api tests 60
management documents 40

Estimate by activity decomposition

Activity name Estimated effort (person hours)
requirements plan 45
requirements validation 12
architecture definition 25
module design 30
interface design 15
documentation 30
developmentd enviroment configuration 20
coding modules 70
test plan 10
unit test 80
system test 45

Gantt chart

ID Activity name Duration (Day) Start Finish Predecessor
1 requirements plan 2 03/04 04/04
2 requirements validation 1 04/04 04/04 1
3 architecture definition 2 05/04 06/4 2
4 module design 2 05/04 06/04 2
5 interface design 2 05/04 06/04 2
6 documentation 2 07/03 10/04 3, 4, 5
7 developmentd enviroment configuration 2 07/04 10/04 3, 4, 5
8 coding modules 3 10/04 12/04 6, 7
9 test plan 1 03/04 03/04
10 unit test 4 04/04 07/04 9
11 system test 2 13/04 13/04 8, 10

Summary

Estimated effort Estimated duration
estimate by size 210 1.2
estimate by product decomposition 355 1.6
estimate by activity decomposition 382 1.7

As for v1, estimate based on code size is shorter because it doesn't take into account all aspect of activities necessary to complete the project. The others esimates take into account more factor such as planning, design, documentation, ecc, resulting in an higher effort estimate.